Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing: header Curb
Fraction of Day workable 10/10
AM cloudy PM Mostly Sunny
Hi 84 Lo 68

Reith Riley had a crew pouring concrete bicycle track from Western to Jefferson on the west side of Main. A second crew poured side walk on the east side of main from Colfax to Washington. they also worked on bicycle track from Colfax to LaSalle on the west side of Main. A third crew worked on pouring curb and Miscellanies pieces from Colfax to Washington. 

A Reith Riley prep crew worked on grading for Bicycle track on the west side from Wayne to Colfax. A second crew worked on grading from Colfax to Jefferson on the east side of the road. A third crew worked on placing bicycle pavers from Marion to Madison on the west side of Main.

Indiana earth had a crew working on rough grading out the west side for bicycle track from Wayne to Colfax. they had a second crew working on removals from Jefferson to Wayne on the east side.

Pemberton Davis worked on the lighting at the round about at Marion. they worked on the Hawk signal at the fire station. They poured cabinet and tesco bases at Western Wayne and Colfax. 

Wisco was on site working on the South East quad of Marion and Michigan.

Slussers was on site doing plantings in the Bartlett round about. 