Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing: header Curb
Fraction of Day workable 10/10
AM Cloudy PM Cloudy
Hi 78 Lo 66
Reith Riley had an Asphalt crew finishing the pavement at Bronson and Main. They had a second crew pouring Header curb on Main Street West side between Jefferson and Western. A Third Concrete crew worked on Pouring driveways on the West side of Main Street between Jefferson and Colfax.
Reith Riley had a prep crew working on the alley approach to the tribune. A second prep crew worked on Placing the filter cloth and 8's under the pave drain areas on the west side of Main from Jeferson to Washington.
Reith Riley had an Asphalt crew come in and pave the approaches on Bronson east of Michigan.
Indiana Earth continued to work on removals on the east side of Main Street between Colfax and Washington.
Woodruff worked on structures between LaSalle and Washington on the west side of Main Street.
Air Marking worked on the traffic Marking details on Michigan at the intersections of Angela, Navarre and North Shore.They also striped Main Street from Ewing to Lasalle.
Pemberton Davis worked on lighting conduit on the west side of Main from Colfax to Washington.
Wisco worked on Michigan and Marion intersection North east corner.
Meeting With:
|
|
|
|
Meeting Date:
|
|
|
|
Regarding:
|
|
|
Construction and
Utilities
|
|
|
ITEMS TO BE
DISCUSSED
9:00 AM Introductions/Sign
in
The Weeks up Coming
Events/Schedule
1.
Traffic Closure Updates
A.
Main St. between Bronson to South Street will
remain one lane of traffic South Bound until the curb and guardrail is placed.
B.
Colfax east of main will be closed for pipe in
the upcoming week.
C.
Western will between Main and Lafayette will be
closed Monday by the City for sewer repair work.
Utility Relocation Issues:
AEP: 1.
Will be working on Michigan from
Western to Colfax in the upcoming weeks.
2.
AEP would
like to move the TESCO Cabinet from the Northeast corner to the South West
Corner.
Robert Henry:
1.
They will finish the work at Madison and Main as
soon as Reith Riley gets Main and South Street opened.
2.
The Vault at Jefferson and Main South West
corner may be an issue but we will avoid it for the time being.
3.
The vaults at Washington and Main South East
corner will be worked on later this year
4.
Robert Henry wanted to know about removing the
lights on the east side of Main St. Which would leave the downtown area on Main
Street in the dark for 2 to 3 weeks while streetlights are being installed on
the west side. This will be delayed until Monday.
NIPSCO/InfraSource: No issues at this time
Comcast: needs to adjust the
vault at Chippewa and Michigan. They are scheduled to be on site in the next
week.
Water Dept The water
deptment has finished adjusting castings on Michigan from Ewing to Sample
Transpo: Reith Riley will
try and have the driveway to Transpo open and in use by the end of next week
Metronet: Will disconnect the WiFI to Downtown on Main Street next
week to allow for stop lights to be moved.
INDOT: Questions: INDOT
was unable to attend
Stakeholder
Questions:
10:00 am 10:10 Break Utility
and Stakeholders can leave
Submittals (List
at Meeting):
Action Items
1
Upcoming work for the week
Reith Riley will work on the East side of main placing the bicycle track,
Drives and working on the cross walks as Pemberton davis gets the traffic
signals completed. They will also work on Main street between Bronson and South
Street. Completing the concrete work, curb work and guard rail. They will start
placing the paver bands between Marion and LaSalle. More landscape work will
continue at Bartlett and Marion.
2 Bronson to South St on Main St open or
closed for Saturday
Main
Street will remain one lane between Bronson and South Street.
2
Cross Walks
Cross walks need to be maintained as the work in the down town area
continues as the east side is removed they must be put back immediately.
3
Corner of LaSalle/ Mich
Still need plans for the corner of LaSalle and Michigan
4
Signs/ status
Pemberton Davis is having issues with some of the design of the signs. I
will email Chris from JPR to make sure all the designers sign match.
5
Paver
ban change order
Structure point still needs to provide the change
order.
6
Bicycle path joints price
The price of $2.00 lft for saw cutting the joints has
been accepted by the city. I will send out a field directive until a change
order can be generated.
7
Light Foundations
The spread foundations will be the larger ones a final
drawing still needs to be provided. It was received an hour after the meeting.
8
Construction Vehicles at intersections
Construction Vehicles need to be kept out of the
intersections to allow foot traffic to move freely. Reith Riley asked if something
could be done to help its employees with parking. With so many workers there is
no where for them to park with out getting towed.
9
Irrigation hook ups on Michigan and
Marion.
Due
to pressure issues the hook ups need to be adjusted
Reith Riley Construction
Concerns/Questions:
Pemberton davis will get the
loops at Angela and Michigan placed on Monday.
Pemberton
Davis will start working on the Hawk Signal for the fire station on Monady or
Tuesday.
Pemberton Davis can not do
the loops for the traffic signals in the down town area until all the lights
are up and running.
City
Concerns/Questions:
Next weekly progress meeting 9-23-16