9-6-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Center Aprons and Curb
Controlling Operation LaSalle to Ewing: Curb
Fraction of Day workable 10/10
AM Sunny  PM Sunny
Hi 87 Lo 72

Rieth-Riley had a concrete crew pouring curb ramp on the east side of Main just north of Marion. Another Rieth-Riley concrete crew poured the upper and lower aprons of the center of the Marion roundabout. A third Rieth-Riley crew poured the remainder of the McDonald's approach along with sidewalk on the east side of Main between Marion and LaSalle.

Pemberton Davis was installing light pole foundations on Michigan St. between Marion and LaSalle.

Indiana Earth was grading in the buffer regions on the west side of Main between Madison and LaSalle.

Airmarkings was on site grinding pavement for permanent striping.

WISSCO was on site working on irrigation at the southwest quadrant of the Bartlett roundabout. 