Wednesday, September 14, 2016

9-14-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing: header Curb
Fraction of Day workable 10/10
AM Cloudy PM Cloudy
Hi 78 Lo 66

Reith Riley had a crew working on pouring the concrete on Bronson Street to the east of Main. A Second Concrete  crew worked on pouring drives on Main Street between Wayne and Jefferson. A third crew worked on pouring header curb from Washington to Jefferson,

Reith Riley had a prep crew working on drives from LaSalle to Washington. They had a second crew working on pave drain from Marion to LaSalle on Michigan,

Indiana earth worked on removals on the west side of Main between Washington and Colfax at the tatoo parlor. They also worked on removals on the east side of Main between Washington and Jefferson.

Me and Tony met with Jim Morris of the Federal Court house and went over the removals and timing.

Pemberton Davis worked on placing conduit on the west side of Main Street between Washington and Colfax. they also poured controller cbinet foundations in various locations. 

Wisco was on sit working in various locations.

State Barricade worked on removing signs and detour markers. They also placed barrels on Wayne street east of Main to funnel traffic down to one lane per Corbett.