Friday, September 2, 2016

9-2-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Center Aprons and Curb
Controlling Operation LaSalle to Ewing: Curb
Fraction of Day workable 10/10
AM Mostly Sunny  PM Mostly Sunny
Hi 75 Lo 55

Rieth-Riley had an asphalt crew that paved the surface and intermidiate of Michigan St. between LaSalle and Marion. They also patched the North East corner of LaSalle and Main.

Rieth-Riley had a curb crew that poured the 3 levels of curbs in the center of the Marion roundabout, including the mountable curb at the level of the pavement. A Rieth-Riley concrete crew also worked at the northeast corner of Main and LaSalle.

Pemberton Davis worked on lighting and signage at the Bartlett and Marion roundabouts.

Indiana Earth was backfilling and grading the areas east of curb on Michigan between Marion and LaSalle.

Slussers was laying sod around the Bartlett roundabout.

WISSCO was working on irrigation on Michigan and Main south of the Marion roundabout. 