Thursday, September 29, 2016

9-29-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing: header Curb
Fraction of Day workable 10/10
AM Cloudy light rain PM Cloudy Light Rain
Hi 68 Lo 48

Reith Riley had two concrete crews pouring side walk on Main Street between Jefferson and Wayne and Colfax and Washington on the east side. A third crew worked on the sidewalk on Marion street east of Michigan.

Reith Riley had a prep crew working on setting pave drain on the west side of Main between Colfax and LaSalle. a second crew worked on prepping sidewalk on the east side of Main between Wayne and Western.

Pemberton Davis worked on pushing conduit on the east side of main from Wayne to Jefferson at various locations. they also worked on Bronson Street.

Reith riley had an Asphalt crew work on patching back Colfax and Marion east of Michigan.

Indiana Earth worked on removals from Western to Wayne on the east side of Main. they also worked on rough grading from Colfax to Washington. 