Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing: Curb
Fraction of Day workable 10/10
AM Sunny  PM Sunny
Hi 88 Lo 75

Rieth-Riley had a concrete crew that poured cycle track on the east side of Michigan St. from the Marion roundabout to south of Madison St. Curb ramps were poured at the northeast and southeast corners of the intersection of Michigan and Madison. 

Rieth-Riley also had 4 prep crews that were utilized for site clearing and cleaning in preparation for the ribbon-cutting tomorrow morning. One of the crews power-washed the aprons of the Bartlett roundabout.

Rieth-Riley also had a crew installing PaveDrain in the parking lane on the east side of Main St between Madison and LaSalle.

Indiana Earth was grading buffer regions on Main between Marion and LaSalle.

Pemberton Davis was working on lighting at the southeast quadrant of the Marion roundabout. They also installed signage at both the Marion and Bartlett roundabouts.

Slussers was installing sod on the west side of Michigan between Navarre and Marion.

Airmarkings was striping Michigan from Angela to LaSalle, Main from Marion to LaSalle, the Bartlett roundabout, and the Marion roundabout. 

WISSCO was working on irrigation on the west side of the Bartlett roundabout.