Monday, September 19, 2016

9-19-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing: header Curb
Fraction of Day workable 10/10
AM Sunny  PM Mostly Sunny
Hi 84 Lo 62

Reith Riley had a concrete crew working on setting Header curb on the west side of Main Street between Colfax and LaSalle. A second concrete crew worked on pouring driveways on the west side of Main Street between Colfax and Jefferson.

Reith Riley had a prep crew working on placing 8's in the pave drain areas between Wayne and Jefferson. A Second crew prepped the bike path area from Wayne to Jefferson.

Pemberton Davis worked on traffic signal and street lighting at the corner of Main and Colfax. 

Indiana earth worked on removals from Washington to Jefferson on the east side. They also had a crew working on grading behind the curb on the west side of Main street from Colfax to LaSalle.

Wisco worked on the irrigation at Main and Marion North East Quad.

State Barricade was on site working on removing detours and signage at the north end that is no longer needed since the road is open.

No comments: