Tuesday, September 20, 2016

9-20-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing: header Curb
Fraction of Day workable 10/10
AM Sunny  PM Mostly Sunny
Hi 84 Lo 62

Reith Riley had a concrete crew pouring header curb on the east side of main between LaSalle and Washington. A second crew is pouring paver band between LaSalle and Marion on Michigan and Main. A third crew is working on side walk on the west side of main on Bronson. A fourth crew is working on pouring curb on Main street between Bronson an south street The curb machine broke down around 10:00am.

Reith Riley has a prep crew removing the south half of the drive at the county court, they are also grading out for the paver band north of Jefferson to Lasalle. A second prep crew is working on placing 8,s for pave drain on the west side of Main between LaSalle and Washington.

Pemberton Davis is working on the Hawk signal at the Fire Station. They are also working on the intersection of Washington and Main.

Wisco is working on the South West Quad of Michigan and Marion behind the side walk.

Indiana Earth is working on removals on the east side of Main between Washington and Jefferson. they are also placing top soil in the Marion round about.