Wednesday, September 28, 2016

9-28-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing: header Curb
Fraction of Day workable 10/10
AM Cloudy light rain PM Cloudy Light Rain
Hi 68 Lo 48

Reith Riley Had 2 concrete crews working on the east side of Main Street pouring driveways at the water department and the Morris.They also poured sidewalk between Jefferson and Washington on the east side. A third crew worked on the driveway approach at the ambulance building on Marion.

Reith Riley's prep crew worked on setting tree grates from LaSalle to Washington on the west side of Main a second crew worked on prepping Colfax to the east and curb line area from LaSalle to Colfax on the East.

Pemberton Davis worked on the east side of Washington and Main and the intersection of South Street and Main.

Wisco worked on Marion on the south side between Main and Mich.

Indiana earth worked on removals from Wayne to Western on the East side of Main. They also worked on rough grading the east side of Main from LaSalle to Washington. 