Thursday, June 30, 2016

6-30-16

Controlling Operation Bartlett: Wall Construction
Controlling Operation Marion: Storm Structure Installation
Controlling Operation Lasalle to Ewing: Removals
Fraction of Day workable 10/10
Hi 82 Lo 60
Weather Am Sunny PM Sunny

Reith Riley had a crew pour the west end of the Marion Roundabout from the crosswalk west. They also had a prep crew working on Main St fine grading from Madison to Marion on Main. Thy where also placing stone on the South East quad of the Marion Roundabout.

Ziolkowski was on site at the Bartlett roundabout forming the inside corners of the concrete walls. Roger from Ziolkowski said that the wall pour would either occur next week Tuesday (6/5) or Wednesday (6/6).

Woodruff had a crew working at the southeast corner of the Marian roundabout installing Str. 145 and connecting pipe to the structure to the south on the east side of Michigan. Woodruff then began installing structures at the intersection of Main and Colfax. While excavating Woodruff hit the MetroNet Line that runs north south across Colfax.

Indiana Earth had a removal crew removing the west side of the intersection of Main and Jefferson. Around 1 pm Indiana Earth hit a MetroNet line running north-south, breaking the conduit. The conduit was excavated across Jefferson and a new conduit is likely needed.

Indiana Earth also performed grading on the west side of Main at Bronson St. and finished removals of curb and pavement on the west side of Main between Western and Wayne.

Pemberton Davis was pulling new conduit across the west side of Main at Bronson St.

Robery Henry worked on the manhole in the center of the Marian roundabout.

Met with Jitin at the saigon Store to review the new entrace.