Monday, June 27, 2016

6-25-16

Controlling Operation Bartlett: Wall Construction
Controlling Operation Marion: Concrete PCCP
Controlling Operation Lasalle to Ewing: Removals
Fraction of Day workable 8/8
Hi 91 Lo 67
Weather Am Sunny PM Sunny

Rieth-Riley had a crew pouring curb on splitter islands in the Bartlett roundabout. Another crew set forms at the Marion roundabout for the southbound lane on the south end of the roundabout. A three man crew asphalt patched the southwest, southeast, and northeast corners of Michigan and Calvert, along with the northeast and southeast corners of Michigan and Indiana.

Indiana Earth continued grading on Marian east of the roundabout. A corner was removed in the old intersection of Marian and Michigan.