Saturday, June 4, 2016

6-4-16

Controlling Operation Downtown: Removals
Controlling Operation Marion: Pipe Work
Controlling Operation Bartlett: Sub-Grade Treatment 
Fraction of Day Workable: 10/10
Hi 76 Lo 60
Weather AM Mostly Cloudy PM Sunny

Rieth-Riley had a 10-man concrete crew which formed the southbound lanes from the Bartlett roundabout to the south end of the Bartlett section on Michigan. Final grading of the formed section will be completed Monday morning prior to pouring concrete. The first concrete truck is scheduled to arrive at 7 am Monday morning.

Indiana Earth has a 3-man crew grading the northbound lanes of the roundabout. A wet spot was found near the south end of the Bartlett section in the northbound lanes that was removed and filled with gravel. No removal work was conducted in the Marian section or on Main St. at Bronson. 