Monday, June 27, 2016

6-27-16

Controlling Operation Bartlett: Wall Construction
Controlling Operation Marion: Concrete PCCP
Controlling Operation Lasalle to Ewing: Removals
Fraction of Day workable 10/10
Hi 89 Lo 64
Weather Am Sunny PM Sunny

Rieth-Riley had a crew pouring concrete pavement in the Marian roundabout. Another 2 man crew was grading for new sidewalk between Wayne and Western on the west side of Main.They had a second concrete crew slip forming curb on Marion Street between Main and Michigan,and down Main on the East side. A third crew worked on had pouring curb at the Bartlett intersection.

Indiana Earth had a two man crew removing pavement on the southwest corner of Main and LaSalle. They also worked at Bartlett grading the North west quad and South west quad.

Woodruff started the day working on Main and ran into several problems due to an electric duct setting in the way. They then went to work on Saint Joe on the west side of St. Joseph south of LaSalle. Another Woodruff crew was working on storm pipe and structures at the intersection of Main and Bronson. Structures 88 and 90 were set on the west side of Main. Structure 88 was mover 6' south from its original location. They also placed castings on four structures between South and Bronson.

Pemberton Davis worked

A meeting was held with Reith Riley to review claims and time. The initial response is no time will be given to extend the intermediate date of Sept 7th. The city is more receptive to off set time with compensation monetarily.  

Madison Oyster Bar gas is being worked on and should be done by tomorrow afternoon.