Tuesday, June 7, 2016

6-7-16

Controlling Operation Downtown: Removals
Controlling Operation Marion: Pipe Work
Controlling Operation Bartlett: Concrete Pavement
Fraction of Day Workable: 10/10
Hi 61 Lo 48
Weather AM Overcast PM Overcast

Woodruff had a crew on the west side of Michigan north of the Bartlett roundabout attempting to tie-in the irrigation system to the water main. They then moved to Michigan and Marion and started on the inlets south of Marion on the west side continuing south.

Rieth-Riley had a concrete crew which poured the center lane of the Bartlett roundabout for Northbound traffic from Sta. 13+00 to 15+00 on Line CC. Forms were then set for continuing the center lane going north. Reith Riley's prep crew came in late and was working at the Bartlett Street Round about working on the subgrade.

Robert Henry completed their electric duct work on the south side of Main west of Marian. Robert Henry is waiting to run their electric duct on Marian east of Michigan until Woodruff runs the new storm pipe across Marian to Structure 237.

Indiana Earth continued grading on Marian. Removals continued on the east side of St. Joseph between LaSalle and Colfax. The majority of the 2 easternmost lanes have been removed in this section. Removal of the guardrails at Main and Bronson has been completed. No removal crews were working on Main Street between Madison and Washington despite the two westernmost lanes being closed.

Pemberton Davis ran conduit to the center of the Bartlett roundabout.

Slushers was working on Bartlett between Michigan and Riverside laying fertilizer and sod.

AT@T adjusted the vault on Michigan north of Bartlett on the west side of the road. 