Monday, June 13, 2016

6-11-16

Controlling Operation Downtown: Removals
Controlling Operation Marion: Pipe Work
Controlling Operation Bartlett: Concrete Pavement
Fraction of Day Workable: 10/10
Hi 93 Lo 71
Weather AM Sunny, PM Sunny

Rieth-Riley had a concrete crew in the morning forming the remaining sections of new pavement to be poured on Monday (6/13).

Indiana Earth had a two man crew grading on Marian east of Michigan.  Indiana Earth also had a two man crew doing removals on Bronson west of Main St. 

No comments: