Monday, June 13, 2016

6-13-16

Controlling Operation Downtown: Removals
Controlling Operation Marion: Pipe Work
Controlling Operation Bartlett: Concrete Pavement
Fraction of Day Workable: 10/10
Hi 85 Lo 63
Weather AM Sunny, PM Mostly Cloudy

Woodruff began excavations and laying pipe for the new storm line down Marian St. Pipe was run from the existing manhole at the old intersection of Main and Marian, and the line was successfully run under the duct bank. Tomorrow the pipe will be tied in to Str. 124A and the connections to auxiliary structures will begin. 

Rieth-Riley had a concrete crew in the morning which poured the remaining sections of the north and south Michigan approaches of the Bartlett roundabout. Rieth-Riley also had a crew which poured curb ramps at the northwest corner of the Calvert and Main intersection and both the northwest and northeast corners of the Calvert and St. Joseph intersection. 

Ziolkowski laid rebar cages for the north and south wall foundations in the center of the Bartlett roundabout. These foundations are scheduled to be poured tomorrow (6/14).

Indiana Earth had a two man crew grading on Marian east of Michigan.  Indiana Earth also had a two man crew grading to the west of the Bartlett roundabout.They worked on removals on Monroe and Michigan

JPR laid out Main Street for removals on the west side south of LaSalle.

Pemberton Davis was working at the intersection of Indiana and Main St. putting in sleeves.

It was determined that the utilities at the intersection of Main and Bronson could not be lowered. Roger called ASI to get the vertical curves set so the utilities would not be an issue.