Tuesday, June 21, 2016

6-21-16

Controlling Operation Downtown: Removals
Controlling Operation Marion: Concrete Pavement
Controlling Operation Bartlett: Round About Walls
Fraction of Day Workable: 10/10
Hi 77 Lo 57
Weather AM Sunny PM Sunny

Rieth-Riley had a concrete crew at Marian forming and pouring concrete pavement in the northbound lanes north of the roundabout. They also poured a sleeper slab on the south side of the Marian roundabout. Rieth-Riley also had a crew on the west side of Main St. pouring sidewalk between Jefferson and Wayne.

Ziolkowski continued setting rebar and formwork for the south roundabout wall at Bartlett. The foundations for the east and west walls were dug but rebar was not placed.

Woodruff had a crew working on the east side of Michigan at and south of Madison St. It was determined that Str. 131A would feed Str. 131 rather than be tied into Str. 219, in order to reduce the number of utilizes the pipe run most navigate. Woodruff also made the connection across Michigan between Str. 129 and 130. Finally, Woodruff relocated a fire hydrant on the southwest corner of Main and LaSalle and replaced a fire hydrant on the west side of Main between Lasalle and Colfax.  

Indiana Earth had a two man crew doing pavement removals on the south side of Jefferson west of Main. Curb and sidewalk were also removed in this section. They also continued pavement removal on the west side of Main between Colfax and Lasalle. 

Phil from NIPSCO met with the owner of Madison Oyster bar and an agreement was reached regarding how the new gas line would be run into the building. Work is scheduled for later this week. 