Wednesday, June 29, 2016

6-29-16

Controlling Operation Bartlett: Wall Construction
Controlling Operation Marion: Storm Structure Installation
Controlling Operation Lasalle to Ewing: Removals
Fraction of Day workable 10/10
Hi 73 Lo 48
Weather Am Sunny PM Sunny

Rieth-Riley had a concrete crew that formed the road section on Marian directly west of the colored concrete crosswalk. They had a second crew pouring sidewalk on Main between Western and Wayne. They had a prep crew working at Bartlett setting side walk grade on the North East and South West Quads

Woodruff installed storm pipe and structures on Main St. between Madison and LaSalle. All structures on Main from the LaSalle intersection north have been installed. They then moved to the North west corner of Lasalle and Main.

Indiana Earth worked on bringing dirt to the center of the Bartlett roundabout inside the concrete walls. They also worked on Main from Bronson to South street cutting grade and cleaning up. They also worked on removals from Wayne to Western on Main west side doing pavement removals.

Th pipe to the new structures under the bridge on Main between Bronson and South Street, will have to be lowered running east to west to get the pipe out of the concrete pavement grade.

The grade North of Madison on Main will need to be wedged to perpetuate drainage.

Pemberton Davis

Zoileski