Thursday, June 9, 2016

6-9-16

Controlling Operation Downtown: Removals
Controlling Operation Marion: Pipe Work
Controlling Operation Bartlett: Concrete Pavement
Fraction of Day Workable: 10/10
Hi 68 Lo 45
Weather AM Partly Cloudy, PM Partly Cloudy, Rain after 4:30 pm

Woodruff had a crew on Main St. south of Madison installing storm structures and piping along the west side of Main St. 

Rieth-Riley had a concrete crew which poured the outside lane of northbound traffic from approximately Sta. 15+00 to 17+00 on Line CC. The remaining aspects of the northbound lanes were formed and these sections are anticipated to be poured tomorrow (6/10). Rieth-Riley had a prep crew on Main at intersections of Calvert, Broadway, and Indiana. Integral curb was poured on Bartlett on west side of Michigan. 

Indiana Earth continued grading on Marian east of Michigan.  Indiana Earth was doing sub-grade treatment at Main St. between Bronson and South Street. They were also doing removals on Main St. at Broadway and Indiana. 

Robert Henry has a large crew that removed the top of the concrete duct bank running north-south on Main St. north of Madison. The three conduits in the top row of the bank were placed just to the west of the second row. A new concrete duct bank was poured in the afternoon. JPR took shots on the new concrete and the top of concrete leaves 4" of cover below the bottom of asphalt. 

Pemberton Davis replaced two westbound signal heads at Main and Calvert and placed one new signal pole at Main and Indiana and one new pole on Michigan and Indiana. 

Bob Kroll from South Bend Water Works will be on site tomorrow at Main and South to locate the 24" water main running along the east side of Main. The area was hand dug today to 7' on the main had yet to be found.