Wednesday, June 22, 2016

6-22-16

Controlling Operation Downtown: Removals
Controlling Operation Marion: Concrete Pavement
Controlling Operation Bartlett: Round About Walls
Fraction of Day Workable: 10/10
Hi 78 Lo 61
Weather AM Sunny PM Sunny

Rieth-Riley had a concrete crew pouring roundabout pavement at Marian. Pavement has been laid for the entire circular portion of the roundabout except for the southeast corner, where pouring the sleeper slab has been delayed by the redesign of structure 145. Rieth-Riley  spent the afternoon forming the southbound lanes of the north roundabout approach. A second crew set forms and poured the sidewalk on the west side of Main between Jefferson and Washington. They also set forms for the walk on the west side of Main between Wayne and Jefferson and graded the new walk between Western and Wayne. 

Woodruff continued working on storm structures on the west side of Michigan at the intersection of Madison. The 18" pipe was installed across Madison, making the connection between structures 131 and 131A. Woodruff spend the afternoon installing the pipe between structure 131 and existing manhole 219. The run required going underneath an existing clay electric duct bank, and the duct bank collapsed as a result of excavation. Casting a new duct bank for the exposed conduit is most likely necessary.

Robert Henry continued running conduit on Marian, and their line has now turned north up the west side of Michigan. 

Indiana Earth had a two man crew removing sidewalk, curb, and planters on the west side of St. Joseph between Jefferson and Washington. They also finished the removals at Marion and Main and Madison and Main. They graded out the subgrade for the asphalt section on Main Street from Madison North to the ally at MarMain Apartments.