Tuesday, June 14, 2016

6-14-16

Controlling Operation Downtown: Removals
Controlling Operation Marion: Pipe Work
Controlling Operation Bartlett: Concrete Pavement
Fraction of Day Workable: 9.5/10
Hi 83 Lo 67
Weather AM Cloudy, Rain, PM Cloudy

Woodruff continued running storm pipe along Marian, and made the connection to Str. 124A. Structures 124 and 125 were placed and connected to 124A. The pipe connections to Str. 126 and 127 were held until tomorrow morning because placing the pipe requires disassembling the temporary crosswalk facilitating access between the Hospital and its Purple Lot. 

Rieth-Riley had a crew at Bartlett that was removing forms and pouring the remaining components of the roundabout colored crosswalks. Rieth-Riley also graded the southeast and southwest corners of Michigan and Calvert for walk and curb ramps.

Ziolkowski completed constructing rebar cages for the north and south roundabout wall foundations. The foundations were poured in the afternoon.

Indiana Earth continued grading in the Marian roundabout section. The dense graded subbase was begun on the north end of the roundabout. Sidewalk removals began on Main St. between LaSalle and Colfax. They also had a crew saw cutting on Main Street South of Lasalle along the buildings. Indiana Earth finished removals on the southeast corner of the intersection of St. Joe and Monroe and began removing the walk at the southwest corner of St. Joe and Wayne.

Pemberton Davis was running conduit across Michigan just north of the Marian roundabout. Their work was completed prior to placement of gravel sub-grade in that section.

WISSCO was running irrigation lines to the center of the Marian roundabout.

During the saw cutting for the sidewalk removals along the buildings south of Colfax on the west side at the Oyster bar a vault was cut into. The vault jets out to the curb line it is roughly 20 by 15. Roger, Toy, Me and Tony Kasar  went down and looked at the basement. After evaluating the situation Reith Riley was instructed to calk and seal the saw cut over the basement. They where also instructed to place support posts under areas of the sidewalk that could be compromised. It was determined that the basement area will need to be filled in, this work will require the utilities entering the building to be relocated. Pemberton Davis will be on site to inspect the electric and Reith Riley is working on getting a plumber.