Tuesday, June 28, 2016

6-28-16

Controlling Operation Bartlett: Wall Construction
Controlling Operation Marion: Concrete PCCP
Controlling Operation Lasalle to Ewing: Removals
Fraction of Day workable 10/10
Hi 64 Lo 61
Weather Am Overcast PM Overcast

Rieth-Riley had a concrete crew pouring the westbound lanes of Marian east of the roundabout. The crew at the Marian roundabout will be moving to the Chippewa roundabout tomorrow and will begin pouring sleeper slabs. The remaining concrete pavement in the Marian section cannot be completed until Woodruff installs structure 145 on the southeast side of the roundabout. Tomorrow, therefore, the controlling operation in the Marian section will be Storm Structure installation. Curb work continued in the Marian section on both side of Main St.

Another Rieth-Riley crew set forms and poured sidewalk on the west side of Main between Western and Wayne in front of the AT&T building. They also poured sidewalk on the south side of Wayne west of Main and poured curb on the NW corner of Main and Western. The west side of Main was graded north of Western.

Reith Riley had a third concrete crew slip forming curb on Main between Marion and Madison on the East and west side.

Indiana Earth had a two-man crew doing removals on the west side of the intersection of Colfax and Main. No removals were done on St. Joseph/Michigan.

Indiana earth also had an operator working the Bartlett St. round about placing top soil and fine grading sidewalk areas.

Woodruff installed a new fire hydrant at the southwest corner of Main and Jefferson. They also replaced a hydrant on the North west corner of Jefferson and Main. They then went to work on Main between Madison and Lasalle on the east side to place two added structures. A field directive was provided to Rieth-Riley this afternoon for the storm structure revisions on the west side of Main at Colfax. Woodruff will begin installing structures at this intersection tomorrow.

Ziolkowski continued setting forms and rebar for the east and west concrete walls in the Bartlett roundabout.

Pemberton Davis installed a signal pole foundation on the southwest corner of Michigan and Sample.

Rieth-Riley and the City of South Bend met again today to discuss Rieth-Riley's request for addition brick paver pay items. The city sent a formal response to Rieth-Riley in the afternoon requesting revised pricing based on clarifications made during the meeting. The city requested pricing for just the reinforced concrete of the non-permeable paver section detail (Division B, Section 1 of 3, Page 139, Detail 6). The city also requested that the quantities for subbase materials of permeable sections be revised to conform with the plans.