Monday, June 20, 2016

6-18-16

Controlling Operation Downtown: Removals
Controlling Operation Marion: Pipe Work
Controlling Operation Bartlett: Round About Walls
Fraction of Day Workable: 10/10
Hi 88 Lo 55
Weather AM Sunny PM Sunny

Rieth-Riley had a concrete crew pouring new sidewalk on the west side of Main St. between Jefferson and Wayne. Rieth-Riley also poured a sleeper slab for the Marian roundabout.

Indiana Earth was grading the Marian roundabout with dense subgrade.