Controlling Operation Downtown: Removals
Controlling Operation Marion: Concrete Pavement
Controlling Operation Bartlett: Round About Walls
Fraction of Day Workable: 7.5/10
Hi 93 Lo 70
Weather AM Sunny PM Thunderstorms

Woodruff continued installing storm pipe and structures on the east side of Michigan south of Marion.

Rieth-Riley had a concrete crew pouring the northbound lanes of Michigan just north of the roundabout between Sta. 45+00 and 42+50 of Line PR-B1. Rieth-Riley also poured curb ramps on the SE corner of Michigan and Indiana, and a crew was grading for sidewalk on the west side of Main between Wayne and Jefferson. They had a second prep crew placing dens graded subbase at Marion and Michigan. 

Indiana Earth continued removing sidewalk on the west side of Main between Jefferson and Washington. Coils for the heated approach to the courthouse were accidentally cut and require repair. Pavement removals took place on the west side of Main between Lasalle and Colfax. The west side of St. Joe was also sawcut between Jefferson and Washington. Finally, Indiana Earth continued grading the Marian roundabout subgrade.

Ziolkowski continued erected rebar cages and formwork for the roundabout walls at Bartlett.

Pemberton Davis was on site in the morning at the Oyster bar relocating the electric conduit this work was completed by 11am They also worked at Indiana and Main. 

Robert Henry continued making their run along the north side of Marian. 

Met with Toy and Roger on the drive ways on the west side of Main between Jefferson and Wayne Street, The drive to the south will be left up an inch so the parking lot can be resurfaced in the future. The second parking lot will need to be milled and paved to get water to drain.