Thursday, June 23, 2016

6-23-16

Controlling Operation Downtown: Removals
Controlling Operation Marion: Concrete Pavement
Controlling Operation Bartlett: Round About Walls
Fraction of Day Workable: 10/10
Hi 79 Lo 68
Weather AM Cloudy PM Sunny

Ziolkowski poured the foundations for the east and west walls in the Bartlett roundabout. PVC for irrigation lines were cast into the column foundations on the ends of both walls. Next, Ziolkowski will begin forming the east and west walls.

Rieth-Riley poured the center lane of the southbound round on the north end of the Marian Roundabout. A second crew was on the west side of Main St. pouring sidewalk between Jefferson and Wayne.

Woodruff installed storm pipe and structures on Main St. between Madison and Lasalle in the morning. In the afternoon after the exposed electrical lines had been retired and removed, Woodruff moved back to Michigan and ran pipe between structure 131 and manhole 219.

Once Woodruff finishes that run and vacates the area, Robert Henry will be on site to run new electric lines and cast a new duct.

Indiana Earth continued removals on the west side of Main between Wayne and Western. They also removed curb and sidewalk from the SW corner of St. Joe and Jefferson and removed sidewalk on the west side of St. Joe between Jefferson and Washington.

Pemberton Davis was working on the southwest corner of the Bartlett roundabout.