Thursday, May 26, 2016

5-26-16

Controlling Operation Marion: Pipe Work
Controlling Operation Bartlett: Pipe Work 
Fraction of Day Workable: 10/10
Hi 84 Lo 64
Weather AM Cloudy, Humid PM Cloudy, Humid

The vast majority of removals have been completed from Marion to Madison on Michigan and Marion. Therefore the controlling operation is now pipe placement.

Reith-Reilly had a concrete crew pouring curb around the concrete sections poured yesterday in the Memorial Hospital Purple Lot, located on the west side of Michigan between Madison and Marian. 

Woodruff was able make the connection between Str. 839B and Str. 824 on the south side of the Michigan and Bartlett intersection while successfully avoiding the 30" concrete pipe and the 12" sewer line.

While doing removals at Bronson and Main, Indiana Earth hit a gas line. The area was secured by police and plans for repair are forthcoming.



Indiana Earth has a one man crew removing sidewalk on the west side of Michigan between Madison and LaSalle. Indiana Earth also continued grading the area for the Bartlett roundabout. They removed two mushy spots and did a proof roll.

Pemberton Davis dug trenches to lay conduit for lighting on Bartlett.

Both Pemberton Davis and Wisco bored to the center of the roundabout. 

Robert Henry was preparing to pour concrete for grates at the northeast corner of the Marian and Michigan intersection.

State Barricade provided one of the missing message boards at Chippewa but has yet to provide the other at Colfax and Michigan. 