Monday, May 16, 2016

5-16-16

Controlling operation: Curb
Fraction of day workable 10/10
Hi 68 Lo 38
Weather Am Mostly Sunny Pm Mostly Cloudy

Reith Riley had a curb crew slip forming Bartlett street concrete pavement sections east and west of Michigan Street. They had  second concrete crew placing curb on riverside and sidewalk on Bartlett street between Michigan and Saint Joe Street. A third crew was prepping for side walk on Bartlett street between Saint Joe and Michigan.

Reith Riley also had a asphalt crew on site finish paving the temporary road from Michigan to Marion. they also did some wedging on the Bartlett street parking garage.

Pemberton Davis worked on the intersection of Sample Street and Main. they also worked Bartlett Street placing conduit for lighting. They also placed the temporary road signs on US 31 for the closure.

Indiana earth was on site doing miscellaneous work moving material.

State Barricade was working on the detours, for the Bartlett street and Marion Street road closure. They also staged barrels and barricades. They are scheduled to close the road tomorrow at 6:00 am.

Met at Lawson Fisher today to review the redesigning of Michigan road drainage at the McDonald entrance. The design is due to electric duck banks running along the curb.

Ferguson was on site working on the vault at Bartlett and Michigan.

Infrasource is still working on the gas line on the west side of Main between Marion and LaSalle.

Andrew, Kevin and Scott started today on the project for the city.