Thursday, May 12, 2016

5-12-16

Controlling Operation: Concrete Paving
Fraction of day workable 8/10
Hi 76 Lo 56
Weather Am Cloudy PM Cloudy Rain

Reith Riley worked until 3;30 due to rain.

Reith Riley had a crew pour the alley approach on the North side of Bartlett between Michigan and Saint Joe. They also had a crew slip forming curb on Bartlett between Michigan and Saint Joe. A third crew worked on grading out the alley on the North side of Bartlett between Saint Joe and Michigan. They then moved to the west side of Bartlett between Main and Michigan and worked on grading out the parking garage turn around.

JPR was on site setting hubs for the garage turn around and for the temporary road being placed at Marion and Michigan.

Indiana Earth worked on the removal of the Mar Main Pharmacy and cutting the grade for the Mar Main Pharmacy.

Pemberton Davis was on site pushing Conduit and cable at the Michigan and Indiana intersection.

Woodruff worked on placing structures on Main Street south of Marion on the West side.They then  started digging and laying out for the new waterline in the same location. While digging for the new line woodruff struck an existing water line at about 3:30 Pm. Bob Kroll and the water dept. then showed up and and worked on shutting off the water and repairing the damage.

Did the RAS Meeting presentation. 8 to 9