Wednesday, May 11, 2016

5-11-16

Controlling Operation: Concrete Paving
Fraction of day workable 10/10
Hi 76 Lo 56
Weather Am partly cloudy Pm partly cloudy

Indiana Earth finished knocking down the Mar Main Pharmacy. They also undercut 2 areas on Bartlett Street where  dry wells set. These areas will be backfilled with 2's. They also worked on grading out the drive for the Bartlett St. parking Garage.

Woodruff placed the endsection on the storm line and the rip rap gab-ions that dumps out to the Saint Joe River. They also worked on laying out the 8 inch watermain on Main Street  south of Marion. The insert valves that were placed yesterday that leak can not get replaced for another 2 weeks.

Reith Riley poured the east bound lane of Bartlett Street between Main St. and Michigan St. They also poured the alley east of Michigan St on the south side of Bartlett.

Pemberton Davis worked on Main and Calvert and Main and Indiana.

Met with Tanner and Chris Chockley about the fiber at Bartlett and Michigan.