Friday, May 20, 2016

5-20-16

Controlling Operation: Removals
Fraction of Day Workable: 10/10
Hi 68 Lo 50
Weather AM Sunny, Partly Cloudy PM Mostly Cloudy

Reith-Reilly had a concrete crew working on side walk on Bartlett St. between Michigan and St. Joseph. The sidewalk on the north side of Bartlett was completed up util the point at which the sidewalk begins to expand from 6' to 10'. The sidewalk ramp on the south side of Bartlett at St. Joseph St. was also completed. On Bartlett St. on the west side of Michigan, a concrete dumpster pad and adjacent curb were poured.

Woodruff completed placement of the majority of structures on Michigan St. between Park and Bartlett. Connection across Michigan is still needed between the structures immediately south of Bartlett St. One additional work day is likely needed to complete all storm sewer work in the Bartlett project.

Indiana Earth  continued removals on Marian and Michigan. Asphalt has been removed on Michigan from as far south as the McDonalds entrance south of Marian. Marian removals (road, curb, and sidewalk) extend west to approximately where the curve connects to Main St.

Nipsco completed there work on the west side of Michigan between Bartlett and Navarre mid-morning.

Infrasource continued work on the west side of Main St. between Marian and LaSalle. Their work closed the far west lane of Main. The two farthest lanes east were barricaded mid-afternoon, restricting traffic to one lane. However, no removals took place in this section.

Pemberton Davis was pushing electric conduit at the intersection of Bartlett and Michigan.

State Barricade placed a few additional signs for maintenance of traffic in the area directly east of 100 Navarre Place. Drums and barricades were placed on Main St. between Marian and LaSalle, closing the two lanes farthest east.

Air Marking provides striping along the temporary road at St. Joseph and Marian, and also along Main St. between Marian and LaSalle.

The weekly progress meeting was held at the City Field Office. Representatives from Memorial Hospital attended and provided a list of requests regarding additions and corrections to existing signage along with some requests for new signage. Complete meeting minutes are attached below.

Permission was granted to proceed with plans to Hydro-Vac the area beneath the existing Fiber Optices line between Bartlett and Riverside. It is estimated that 300' of line needs to be lowers 2' in order to not be in the way of the Marian roundabout foundation.

A meeting was held between Reith Riley and the City of South Bend to resolve storm structures in the plans lacking details such as height and piping. 18 structures were investigated and the City of South Bend provided directives for structure fabrication.


Meeting Agenda
Meeting With:
Reith Riley & City of South Bend


Meeting Date:
5-20-16


Regarding:
Two Way Conversion Weekly Progress Meeting

Construction and Utilities



ITEMS TO BE DISCUSSED

9:00 AM Introductions/Sign in

The Weeks up Coming Events/Schedule
1.      Update: Reith Reilly started the Michigan St closure on Tuesday to begin removals and storm work. 
2.      Upcoming: Reith Reilly is still working on removing concrete on Marion, east of the proposed roundabout.  Coming up next week, Reith Reilly expects lane restrictions in multiple places.  The west side of Main St. between South and Bronson will be closed.  The west lanes of Main will also be closed between Lasalle and Colfax.  This closure will happen in phase with the closing of eastern St. Joe St. between Lasalle and Colfax.  Next week, Reith Reilly plans to begin removals in the downtown streetscape area while they finish storm work at the Marion and Bartlett roundabouts.

Utility Relocation Issues:
AEP:   AEP is out of Reith Reilly’s way both the Marion and Bartlett roundabouts.  The relocation of their 3 phase tie at the Chippewa intersection has been set and they are on track to be out of the area by 6/2.

                Robert Henry: Robert Henry has completed their work on the east side of Main St and plans to be done working on Western and at the intersection of Marion and Michigan St today.  They plan to start work on Washington St on Monday so that they remain in sequence with Reith Reilly’s work.

NIPSCO/InfraSource:  NIPSCO has no further work to do in the area of the Marion or Bartlett roundabouts.  By the end of the day, NIPSCO’s 8” pipe on Main St will be retired.  They also have plans to be done working on Lafayette today so that they are off of the temporary arterial roadway ahead of next week’s additional road closures.  Other work on Main St, between Lasalle and Colfax, will be completed by next Thursday so that they are out of Reith Reilly’s way.

            
Comcast: Jay relayed that an area crew should be pulling their fiber on Chippewa in the next few days.  They have plans to be out of the Chippewa intersection well before the 6/5 deadline.  Jay hopes to be off of the pole at the Marion roundabout before Monday, leaving AT&T as the sole utility left on the pole. 

US Signal:  US Signal didn’t show up to the meeting, but after talking with Charlie O., it appears as if they plan to send a bore crew out on Monday to begin pushing conduit on Monday.

AT&T:  AT&T was a no show and I haven’t heard much from Dennis.  The vaults at Michigan and Bartlett have been backfilled and are no longer a concern.  Reith Reilly has an estimate on the price to reroute from Woodruff and will pass this on to Myron.  AT&T also appears to be using the vault of the JMS building as a hub.  They will need to relocate their lines before the vault can be closed down.  At the Marion roundabout, AT&T still has an overhead line connected to a pole.  At this point, it appears as if AT&T will need to hold the pole while Reith Reilly finishes their storm work on Monday, 5/23.

Water Dept:  Ed from the Water Department brought news that the valve breakage on Main St, north of Lasalle, has been repaired.  The other breakage, located on Lasalle, is set to be fixed by the second weekend of June.  The water line near the Mason facility on Main St needs to be relocated, but Woodruff is still waiting on the insert valves to be manufactured.

                 INDOT: INDOT was a no show.

Transpo:  Transpo just wanted to confirm the upcoming lane closures with Reith Reilly and ensure that their buses will still have a means of transport through the lane restricted zones.

Metronet: There appears to be a very shallow fiber line located on Michigan St crossing Bartlett at the site of the proposed roundabout.  An estimated 300 LFT of line needs to be lowered so that it is not in the way of the roundabout foundation.  This will take about 2 days’ worth of work, is scheduled to begin on Monday.  Concurrently, an undistributed 2” PVC will be added in the area for future use.  Ben noted that this issue might be run into again at the site of the Marion roundabout and perhaps throughout the remained of the job.  As a final note, Ben wanted to emphasize the importance of being careful with such a large excavator on Michigan St near Bartlett.  Scott from Reith Reilly mentioned the idea of conducting some pothole depth checks to ensure no Metronet lines are accidently pulled. It was also suggested to run an additional conduit while lowering the current on for future use.

MCI: Quentin from MCI didn’t show.  They were set to begin their work in phase with Reith Reilly’s crew next week, but I will call to confirm that a start date has been set.


Stakeholder Questions
Memorial:  Larry mentioned that many patients have arrived to the Memorial campus frustrated with the current signage.  He stayed after the meeting to talk with Myron about his recommendations for additional signage and safety concerns.  Tony with Reith Reilly offered to open part of Bartlett to improve vehicle access to Warner and Navarre Street parking.  Larry would like to see Indiana Earth using a wet saw to keep the dust cloud from saw cutting the pavement to a minimum.  Further, though temporary striping exists in some pedestrian areas, Memorial would like some sort of fencing to be put in place to funnel pedestrians to the correct areas.  Finally, Larry wanted to emphasize the need for a direct walkway from the purple lot (located across from the field office) to the hospital.

Additional RW and Encroachments:
               Division A
1.      Sandra V Case ( Keys )
-         Both the Case and Palmer houses have had asbestos tests done.  Each showed trace amounts, but the remediation required won’t be an issue.  The keys to the Case house will be handed over today.  Utilities plan to disconnect from both houses before demolition begins next week.
               Division B
1.      Burkhart sign/foundation
-         The Burkhart sign is being removed today.  As for the foundation, the City would like for it to be removed to a depth of 5’.  A time and material analysis on Burkhart’s price quote for foundation removal will be conducted to meet this request.

Submittals (List at Meeting): We are currently waiting for the revised drawings regarding the tree grates as well as a color code (RAL #) for the proposed crosswalks.

Action Items
1.      QC/QA HMA
-         The City is waiting for the price from Reith Riley.
2.      Redesign on Mich/Marion
-         The East side of Michigan will now include 5 (identical) special shallow structures.  These drawings will be distributed by early next week.  The most pressing issue is currently the detail regarding the connection to the west side of Michigan St as Reith Reilly plans to begin work in this area on Monday, 5/23.
3.      Chase Tower (Main Street)
-         Chase has said they will take responsibility for the sidewalk located above their vault.  They plan to backfill the vault in this area and conduct their work in sequence with Reith Reilly.  There have been some concerns regarding the safety of Reith Reilly’s crew when working in the area of the building, especially during times of gusty winds.  Toy will follow up on this.
4.      RFI #4 Permeable Block

5.      Side Walk Closures
-         We discussed the importance of Reith Reilly keeping up with posted sidewalk closures near the worksite.  This goes hand-in-hand with some of the concerns Larry and Memorial brought up about pedestrian access routes to the hospital.
6.      Mar Main Delay
-         Reith Reilly stated that it’s hard to define the amount of time they were delayed since they were able to work in some other areas during the delay.  Right now, they are an estimated 5-6 days behind schedule.  Moving forward, Corbitt would like to see all issues and delays brought to light immediately and in writing.  He introduced the idea of a spreadsheet being used to track the contractor’s notices and subject them to an internal review process.  Toy, Myron, and Roger plan to meet about the creation of such a spreadsheet on Monday.
                               
Reith Riley Construction Concerns/Questions:
New drawings regarding traffic control on Michigan St near the Fire Station are coming.  As for the trench drain that was scheduled to be taken out of the design, Woodruff told Reith Reilly that the drain has already been ordered and that there is not a restock price.  As a result, Corbitt said the City would keep the drain, but still follow through on the changes to the design.  Though there is still no information regarding the concrete joint sealer, Tony wants to make sure a sealer that comes in a limestone color is chosen so that the product looks professional.  Tony was also concerned about a few inlets on Bronson St that remain unaccounted for.  Reith Reilly is meeting with Roger at 2 pm to discuss their problems with Structure Point and the problem structures on the west side of Main St.  Finally, we discussed moving the “Welcome to South Bend” from Michigan and Chippewa St to a different location.  The City will remove the sign on 6/6 once closures have begun in the area.
                             
 Next weekly progress meeting 5-27-15




No comments:

Post a Comment