Controlling Operation: Road Closure
Fraction of Day workable 10/10
Hi 62 Lo 44
Weather Am Cloudy Mist Pm Mostly Cloudy
State Barricade was on site and closed 933 at Lassalle at
6:30 AM and then closed at Park Street at around 7:30. Corbett had Navarre and
Michigan and Madison and Main put on red flash. He also wants a 3 way stop at
Madison and Michigan. Michigan was closed at Lassalle for 2 hrs while a message
board was moved to help alleviate the traffic from entering the Riverside
community. We also added signs on the bypass east and west of 31. We added
signs on Park and Main for the Hospital. They placed 2 message boards on Howard
east and west of Niles for the 4 way stop. The big panel sign on US 31 was not
placed today
Reith Riley had a concrete crew pouring the integral curb on
Bartlett Street east of Michigan. They also worked on forming the sidewalk on
the North side of Bartlett east of Michigan.
Indiana Earth worked on removing pavement at Bartlett and
933 and also at 933 and Marion.
Pemberton Davis worked on removing the traffic signals at
the Marion Street intersection and they also turned all the above mentioned
lights to flashing red.
Woodruff worked on the pipe structures at Bartlett to the
North. Once the layout work was completed it was determined that an electric
vault on the east side would be in the way of the Storm sewer. Chris
Ferguson was backfilling the vault placed on Bartlett and Michigan.
Infrasource is working on Main st. west side between Lassalle and Marion.
The Burkhart sign is going to be removed by Burkhart.
Chockley
came out on site and will come up with a plan and send it to me asap.