Monday, May 2, 2016

5-2-16

Controlling Operation: Structure Placement
Fraction of day workable 10/10
Hi 58 Lo 44
Weather Am Cloudy light rain PM Cloudy mist

Woodruff poured inverts in structures on Bartlett between Michigan and Saint Joe. They also placed pipe and structures on Bartlett Street between Michigan and Main Street.

Indiana Earth placed topsoil behind the side walk and ADA ramps on Michigan St. between Bartlett and Angela. They then went down to Chippewa and started removals.

Reith Riley placed asphalt around the ADA ramps on Michigan between Bartlett and Angela. The ADA ramps can now be opened to the public.

Pemberton Davis worked on pushing conduit and connecting the conduit to the hand holes and cabinet foundations at Michigan and Indiana.

Dale Clink started working on the Division B project.

Dale and I went to the Chase tower and measured the basement to the East to determine if the basement projects out under the side walk of Michigan. The basement is 11 feet under the sidewalk it is 126 feet long and 12 feet tall.

Had a meeting with Chris Chockley of JPR, Ben Hudson of L@F and Patrick Wooden of ASI, Patrick Kerr, Roger Nowrat and Toy Villa. This meeting is in regards to RFI #4 permeable blocks. After reviewing the diffrent typical sections on the diffrent plans and the special provisions. ASI will respond to the RFI. by instructing the contractor to build the typical section as shown per plan.  