Controlling Operation Asphalt Paving
Fraction of day workable 8/8
Hi 52 Lo 42
Weather Am drizzle Pm cloudy

Reith Riley placed the base and intermediate on the temporary drive for Mar Main. They then paved the drive ways on Bartlett Street east of Michigan. Once that was completed the went to the west side of Michigan and worked on the parking garage drive.

AT@T had Ferguson on site working on the vault. It appears that there is not enough slack in the lines to get them moved into the vault. Thus it will cause an issue delaying getting AT@T out of the way.

Robert Henry was removing light poles at the Marion St Intersection with Michigan and Main St.

Aldridge was working at the intersection of Michigan and Bartlett in the North Bound right lane.