Controlling Operation: Removals
Fraction of day workable 10/10
Hi 69 Lo 48
Weather Am Sunny Pm Mostly sunny

Reith Riley had a concrete  crew working on side walk on Bartlett St.between Michigan and Saint Joe.

Woodruff had two crews on site working at the intersection of Bartlett. One placing pipe and structures in the North East quad and a second placing pipe and structures in the south west quad. Chris Chockley was on site to look at a the south west quad the new storm line running north and south is in conflict with an existing drain line running east and west. A structure will be placed to intersept the existing and new storm line.

Indiana Earth had 2 removal crews working. One crew worked on Bartlett and the second worked on the Marion intersection. A third crew worked on Bartlett street west of Michigan cutting grade for sidewalk.

Pemberton Davis worked on removal of signs at the intersection of Marion and Michigan.

Ferguson was on site and finished backfilling the AT@T vault at Bartlett. This work was completed by noon.

Infrasource was still working on the west side of Main Street between LaSalle and Marion. This area was to be where Reith Riley was to be working on the street scape area

State Barricade was on site bringing more signs to closure of Bartlett and Marion.