Friday, May 27, 2016

5-27-16

Controlling Operation Marion: Pipe Work
Controlling Operation Bartlett: Sub-Grade Treatment 
Fraction of Day Workable: 10/10
Hi 79 Lo 64
Weather AM Cloudy PM Cloudy

Woodruff began pipe and structure work on the north side of the new Marian between Michigan and Main. Piping and one structure were placed. 

Indiana Earth had a one man crew and a dozer doing grading at the Bartlett roundabout. Removals continued on the west side of St. Joseph between Marian and LaSalle. Removals also took place on the west side of Main St. between South and Bronson. 

Pemberton Davis poured four light pole foundations on Bartlett between Michigan and Main. 

The weekly progress meeting with utilities and stakeholders took place in the morning. Meeting minutes are provided below. 


Meeting With:
Reith Riley & City of South Bend


Meeting Date:
5-27-16


Regarding:
Two Way Conversion Weekly Progress Meeting

Construction and Utilities



ITEMS TO BE DISCUSSED

9:00 AM Introductions/Sign in

The Weeks up Coming Events/Schedule
·        Update: Reith Riley continued removals around Marion and Main and started removals on the west side of Main St. between South and Bronson Streets.  Storm work is finished in the Bartlett area and Woodruff has begun work at the Marion intersection.
·        Upcoming:  Looking ahead, the next phase of lane closures is scheduled to begin on Tuesday, May 31.  This closure involves closing the east side of St. Joseph St. and the west side of Main Street between LaSalle and Colfax.  In the area of this closure, Reith Riley will begin concrete, curb, and sidewalk removals.  Meanwhile, grading and concrete work is scheduled to begin at the intersection of Michigan and Bartlett Streets next week, and pipe work will take place at Marion and Michigan as well.

Utility Relocation Issues:
AEP:   AEP has an existing sidewalk vault on the southeast corner of Bartlett and Michigan that will need to be raised so that it is in line with the new curb.  Bob from AEP has talked with Tony (Reith Riley) to identify the street lights to be removed in the downtown area.  This work will begin next week.  In the southern portion of the project, at Chippewa Ave, AEP has cut service to the Palmer and Case houses, and work is underway to reroute overhead lines away from the Chippewa pole.  Bob will talk with the contractor on site to ensure power to the traffic signal at the intersection of Michigan and Chippewa remains until the closure on June 6.

Robert Henry: Robert Henry is done with their work on Michigan, at Marion Street, as well as on Main, at South Street.  They will begin work to cross Main at Western Ave next week.  Robert Henry was reminded that they need to tie-in on the eastern side of Western Ave before Reith Riley comes through.  Once they are finished on Western Ave, they will move on to Jefferson St.


NIPSCO/InfraSource:  Brian, from Infrasource, relayed that as a result of their work this week, they have a 4” conduit pulled halfway across Main just south of Colfax Ave.  To finish crossing the street, they must close the west side of Main between Colfax and Washington St.  Brian plans to initiate this closure after the morning rush hour traffic on Tuesday, May 31.  Work will break during the afternoon hours to be completed overnight on Tuesday.  Phil of NIPSCO stated that his lines that are in conflict with the project north of Colfax Ave will be completely retired on Tuesday, May 31.  Once work is completed in the Columbus Court area, Infrasource will permanently patch the sidewalks that are not going to be removed by Reith Riley.
     
Comcast: Jay was unable to attend, but he told me earlier this week that he remains on schedule to be out of the way at Chippewa Ave by the scheduled deadline.  Comcast has placed their conduit and cables and splicing is currently scheduled to take place on June 2 or 3.

US Signal:  Similar to Comcast, Charlie O. relayed that US Signal has placed conduit and cables and plans to splice in time to meet the June 6 deadline.

AT&T:  Regarding the pedestal that remains near the Burkhart sign, I talked with Dennis and he will have a crew come to remove it if it is an issue.

Water Dept.:  Ed with the Water Department brought to light some concerns regarding the closures blocking the Water Works’ Customer Service Office drive on the east side of Main Street.  The east side of Main is projected to be closed in about 3 weeks.  Ed will make sure a representative from the Customer Service Office is present at the progress meeting in the coming weeks.
                         Eight inch insert valve are in and will be installed the coming week.

INDOT: INDOT had a few minor concerns regarding the relocation of SR 933 signage and signal timings.  The City will relocate SR 933 signage per plan and has plans to adjust signal timings in mid-June.

Transpo: Michael from Transpo just wanted to confirm a meeting to discuss the bus lot’s temporary access lane during the lane closure on the east side of Main between South and Bronson Streets.

Metronet: Ben, with Metronet, relayed that if his 3” conduit is placed by Wednesday, June 1, work on Thursday and Friday nights will finish everything in the Bartlett area.  As a side note, Ben reiterated the need for Indiana Earth to be extremely careful when excavating.  After narrowly avoiding a huge outage last week, Ben would like to be on site to observe Indiana Earth’s excavation for the remainder of their work on Main Street.

              
               MCI :  MCI has relayed that they are completely out of the way on Main at South Street.

Stakeholder Questions:
Memorial Hospital:  Larry with Memorial brought a few topics up for discussion.  First, he commended the sign changes that have occurred but suggested a few more for patients that aren’t as familiar with the construction area.  Second, after a light pole was taken out by a truck last week, Larry was concerned about how to stop trucks from entering the area and causing damage.  Finally, Roger (City of South Bend) will set a meeting with Larry and the manager of Mar Main Apartments to discuss concerns regarding safety of new tenants with Memorial employees speeding through the nearby alley.

10:00 am 10:10 Break Utility and Stakeholders can leave

Submittals:  I am waiting on an overdue submittal from Structure Point.  I will contact them again today so that it can be relayed to Reith Riley as soon as possible.

Action Items
1.      QC/QA HMA:  Corbitt would like to have an internal meeting with Toy and Roger regarding the price change proposed.  He plans to have a decision by Tuesday, May 31.

2.      Redesign on Mich/Marion:  Scott (Reith Riley) brought to light concerns regarding the amount of change orders being placed.  With so many conflicting change orders, his team is confused and unable to keep a tight schedule.  Further, Scott requested to see revisions come in a more organized format.  Moving forward, Reith Riley would like to see only the final change order and Corbitt ensured the City would work with Reith Riley to get these change orders out in a timely manner.  All previous change orders will be resummarized and Reith Riley will assign a cost to the time spent working on change orders that were subsequently overridden.

3.      Barricades:  Reith Riley needs to ensure their subcontractors are re-closing barricades following the end of the work day.

4.      RFI #4 Permeable Block:  A letter has been drafted by Scott and will be passed along soon.

5.      Side Walk Closures:  In general, the City would like to see Reith Riley doing a better job of advertising sidewalk closures.

6.      Brick Manholes:  The City will get a change order to Reith Riley shortly.  The plan is to utilize the brick manholes after covering them with a spray-on concrete mixture.  The City will get the dimensions and depths of the manholes in question to Reith Riley soon.

7.      Concrete Joint Sealant:  Similar to Item 1, Corbitt will have a decision to Reith Riley Tuesday, May 31.

8.      Case House:  All electric and water have been cut to the Case and Palmer houses at Michigan and Chippewa.  NIPSCO has a crew out shutting off the gas supply to the houses today.  Asbestos treatment has been completed and Indiana Earth is scheduled to begin demolition on the houses on June 6 per their IDEM permit.

9.      Status of Signal Changes/Future Change Holes:  The signals at the intersection of Michigan and South St are going to be put back in operation.  The traffic signals at the intersections of St. Joe & LaSalle and St. Joe & Colfax (potentially those at St. Joe & Washington and St. Joe & Jefferson) will be changed to string poles instead of mast arms.  A change order will be coming in the next week.  Once the shop drawings are obtained and stamped, it will take about 8-10 weeks for the poles to be received.
                             
 Next weekly progress meeting 6-3-15


No comments:

Post a Comment