Tuesday, May 10, 2016

5-10-16

Controlling operation: Concrete Paving
Fraction of Day Workable 0/10
Hi 65 Lo 48
Weather Am Rain  PM Rain

Pemberton Davis removed the traffic signal mast arms,signals and poles at the intersection of Bartlett and Michigan. They then went home for the day.

Indiana Earth worked on the demolish en of the Mar Main Pharmacy

Reith Riley had a small crew work on setting forms on Bartlett St.between Main and Michigan. They went home when the rain got heavier.

Woodruff worked on placing the insert valves on the 8 inch water line on Main st just south of Marion. The insert valves that where placed leaked due to the pipe size outer diameter is an odd size.
Bo Kroll was by and will be back tomorrow to try and help with this issue, because he does not want to shut the water of to the area. Woodruff then worked on filling the gab-ions at the river with rock.

AT@T cut its own line at the vault at Bartlett and Michigan yesterday at around 4:00 pm. This line cut caused Ferguson to lose a day of demoing on the vault.

Travis Tredway started at the office today.


No comments: