Thursday, May 5, 2016

5-5-16

Controlling Operation: Fine Grade
Day workable:10/10
Hi 62 Lo 42
Weather Am Sunny Pm Sunny

Woodruff was not on site today.

Reith Riley worked on pouring the 9 in concrete pavement on Bartlett St. They paved the East bound lane from the cross walk to the end of the run going east. They also had a crew placing curb on Bartlett St.on the south and North side from Saint Joe st to the end of the concrete pavement to the west. Reith Riley had a third crew fine grading the stone out in front of the curb Machine.

Weaver Booz was on site to test the subgrade and the concrete pavement. They made beams for open to traffic.

Indiana Earth worked on cutting the on Bartlett St. between Michigan and Main. They also worked on placing subbase on the Bartlett street dives and alleys. They where unable to complete this work due to the AT@T pole that is still not removed. Reith Riley sent me an Email notifying me of the delay and loss of production due to this pole not being removed when it was suppose to be.

Pemberton Davis removed the Traffic signal pole on the North West corner of Michigan and Bartlett. The wiring to the Pole on the South West corner runs through the foundation. This means if the foundation is removed the cross walk will no longer work.

A meeting was held to discuss the Mar Main demolition which is not taking place as scheduled due to the utilities are not being disconnected. The demolition was scheduled for today, but NIPSCO still has to disconnect the line at the alley, if things go well that will happen tomorrow. Indiana Earth will then have to apply for a permit from the building dept. which they will have to also do for the electric, which they have not done yet. If the demolition and temporary road are not completed by the 17th. The intersection will still be closed. alternate scenarios were discussed to maintain emergency vehicle access to the Riverside neighborhood.

Also discussed was the deliveries to the McDonald's, mike Guzik will have Ben get with me and talk with the Manager of McDonald's.

Mike Guzik is also going to look into the type of material used to seal the concrete D1 joints.

Ferguson was working on the vault on Michigan St witch will be located on the North west quad of the new round-about.