Controlling Operation: Subgrade Preparation/concrete paving
Fraction of day Workable 5/10
Hi 58 Lo 44
Weather Am light Rain PM Cloudy/Mist

Indiana Earth removed curb and sidewalk on Main St between Marion and Madison.This work is in conjunction with the watermain  work. They also placed compacted agg on Bartlett between Michigan and Main St. They also placed compacted agg on the  alley approach south of Bartlett between Michigan and Saint Joe.

Reith Riley had a crew placing forms on Bartlett between Main and Michigan. They also formed the ally to the north on Bartlett between Michigan and saint Joe.

Ferguson Started working on the AT@T vault on the southwest quad of Michigan and Bartlett.

Indiana received the permit to demo the Mar Main Pharmacy.

Jessie started working on this project today.