Controlling Operation: Structure placement on Bartlett
Fraction of Day workable 10/10
Hi 69 Lo 48
Weather Am Sunny Pm Sunny

Indiana Earth placed subbase on Bartlett Street between Saint Joe and Michigan Street. They started by bringing in 2 loads of gravel 53's. They then switched to slag 53's after requesting additional pay they were denied.

Woodruff placed structures on Bartlett between Michigan and Main. They then moved the firehydrant at the corner of Bartlett and Saint Joe. They then moved to the intersection of Main and Marion and worked on locating a waterline that will need to be relocated.

Pemberton Davis worked on the intersection of Michigan and Indiana. They set a hand hole and worked on connecting conduit.

JPR was on site and laid curb lines on the east and west side of Michigan.

The electric line that Woodruff hit Friday in the old Memorial parking lot west of Michigan will need to be lowered. I called Denis bunch again about the pole in the ally between Saint Joe and Michigan the splicing was suppose to be done and the pole removed, This has not happened yet. Reith Riley has kept working around this pole and will soon be to a point where they will have to work in a different area.

The Gas was disconnected to the Mar Main Pharmacy today.