Controlling operation Pipe structure placement on Bartlett
Fraction of day workable 10/10
Hi 55 Lo 48
Weather Am cloudy Pm partly sunny

Reith Riley had a crew working grading out ramps. North of Bartlett on the west side of Michigan.
2 labor 1 teamster 1 opp  1 truck 1 tri-axle 1 excavator

JPR on site doing layout for Ramps
2 men 1 truck

Pemberton Davis worked on setting handholds at Indian and Michigan and Calvert.
2 labor 1 foreman 1 arrow board 1 truck 1 utility truck 1 trailer

State Barricade was on site setting detour signs up around the hospital.
2 labor 1 truck

Woodruff placed pipe on Bartlett from Riverside to Saint Joe.
Set structures 805 and 807
2 operators 1 foreman 2 laborer 1 track hoe 1 loader 1 air compressor

I got with Tony to review the tree removal that will take place on Bartlett tomorrow.

During the removals at Riverside a conduit was cut. the conduit was not live. I Had Reith Riley repair the conduit for future use.

Chris Chockley was on site we review a ramp and the work taking place on Bartlett.

The City was working on the intersection of Saint Joe and Bartlett. A void had developed around a structure at that intersection.