Controlling operation Pipe structure placement on Bartlett
Fraction of day workable 10/10
Hi 55 Lo 48
Weather Am cloudy Pm partly sunny
Reith Riley had a crew working grading out ramps. North of Bartlett on the west side of Michigan.
2 labor 1 teamster 1 opp 1 truck 1 tri-axle 1 excavator
JPR on site doing layout for Ramps
2 men 1 truck
Pemberton Davis worked on setting handholds at Indian and Michigan and Calvert.
2 labor 1 foreman 1 arrow board 1 truck 1 utility truck 1 trailer
State Barricade was on site setting detour signs up around the hospital.
2 labor 1 truck
Woodruff placed pipe on Bartlett from Riverside to Saint Joe.
Set structures 805 and 807
2 operators 1 foreman 2 laborer 1 track hoe 1 loader 1 air compressor
I got with Tony to review the tree removal that will take place on Bartlett tomorrow.
During the removals at Riverside a conduit was cut. the conduit was not live. I Had Reith Riley repair the conduit for future use.
Chris Chockley was on site we review a ramp and the work taking place on Bartlett.
The City was working on the intersection of Saint Joe and Bartlett. A void had developed around a structure at that intersection.
No comments:
Post a Comment