Wednesday, April 13, 2016

4-13-16

Controlling Operation : Pipe and Structure placement
Fraction of day workable 10/10
Hi 50 Lo 29
Weather Am Sunny Pm mostly sunny

Reith Riley had a crew working on pouring ramps on the west side of Michigan Street North of the river to Angela Boulevard.

Indiana Earth had a crew removing trees on the northwest corner of Bartlett and Michigan. They then worked on prepping the west side of Bartlett street phase 1 of the parking garage drive.

Woodruff worked on placing structures on Bartlett. while working from Structure 803 to structure 802 an unidentified concrete pipe was uncovered at an elevation in conflict with the flow line of the new storm sewer. Toy and Chris Chockley were on site to investigate the situation. it appears to be a secondary overflow line of the sanitary sewer. Chris will propose a solution. a second conflict was also discovered. with the duct bank running down the center of Bartlett. The conflict comes into play with the structures on the South side of Bartlett can not be hooked up to the trunk line on the north side. This is also being looked into by Chris Chockley.

Pemberton Davis worked on Michigan road placing hanholes at the intersections of Calvary  and Indiana ave.  