Thursday, April 21, 2016

4-21-16

Controlling operation:20 inch water main
Fraction of day workable 5/10
Hi 73 Lo 47
AM Rain PM Rain

Most work was rained out.

Indiana earth had a crew on site to place stone. They where rained out at 11:00

Woodruff finished placing the 20" water main at Bartlett.

A meeting was held a the city building today with Toy, Corbitt, Jitin, Roger, and Michael. This meeting was to go over the utility and property issuse and anything else that could delay this project.