Thursday, April 14, 2016

4-14-16

Controlling Operation : Pipe and Structure Placement
Fraction of Day Workable 10/10
Hi 65 Lo 34
Weather Am Sunny Pm Sunny

Reith Riley had a crew pouring side walk ramps between Angela and Bartlett on the West side.

Indiana Earth finished prepping on Bartlett Street to the west of Michigan behind Memorial Hospitals parking garage.

Woodruff set structures on Riverside and the intersection of Bartlett. After discussion with Chris Chockly and Toy we will eliminate structures 808 and 810 due to a conflict with a phone duct bank.
An abandoned sewer line was encountered while placing the truck line from structure 802 to 806.

 I attended a meeting with RAS