Thursday, April 21, 2016

4-19-16

Controlling Operation:Water Main Relocation
Fraction of Day Workable 10/10
Hi 79 Lo 56
Am Mostly Sunny Pm Cloudy


Reith Riley worked on pouring the ramps on Michigan between Angela and Bartlett on the East side.

Woodruff worked on relocating the 20 inch water main on the west side of Michigan. They placed the shut offs and elbows.

Pemberton Davis worked on the intersection of Indiana and Michigan placing peds.

Indiana earth worked on grading out for curb on Bartlett.

Becca Matthys will be organizing the smart sheets spread sheet.