Fraction of day workable 10/10
Hi 58 Lo 47
AM Cloudy PM Cloudy
Woodruff worked on
Indiana earth placed stone on Bartlett street between riverside and Saint Joe
Pemberton Davis pushed conduit on Main Street
Reith Riley poured sidewalk and drives on Bartlett Street.4-22-16 One-way to Two-way Street Conversion
Met with Tony Kasar, Phil Griffen and Infrasource about the work taking place in the downtow area. Infrasource will add a third crew to help try and stay out of the way o Reith Riley
Weekly progress
meeting
Introductions were made.
Reith Riley gave an over view of the upcoming work for the
next two weeks. They will be closing down Bartlett Street between Saint Joe and
Riverside on Monday 4-25-16. Starting with removals and placing pipe in this
area. They will then move to the west side of Bartlett and work between
Michigan and Main Street placing asphalt and building the drive to the parking
lot garage. Once that is done they will start building the Bartlett Street by
removing the parking lot. At the same time they will be working on the south
end at Chippewa phase 1.
AEP
has its relocation work done at Chippewa. They will still have to remove some
light poles as needed once Michigan closes. They also have work on Marion that
will take place once the road closes. Tony macia was not at the meeting to
discuss the work at Chippewa The
work on Main St north of Chippewa is completed, the old pole was cut at base. I
had another job south of Chippewa on Michigan north of Barbie St that is also
completed, this removes the tap from the pole line on Chippewa and is fed from
the south. The next phase is to re-route the feed to an existing three phase
line east of Michigan, which should be completed weather permitting before or
by the second week in May, after which I can have the pole line on Chippewa
between Main and Michigan removed. We need to be careful here there is a
service for the traffic signals at this intersection (Chippewa & Michigan)
I need to know when this can be removed. I also met with Phil Johnson from
Pemberton Davis regarding service for some new TESCO boxes at the intersections
of Indiana and Calvert on Main and Michigan, he will contact me as he moves on
to other intersections. I will return Monday if you have any questions. I left
a message with a contact at Windstream to call me on the status of their
facilities.
Nipsco relocation work at Bartlett is
done. Nipsco is now concentrating their efforts on the downtown area. Reith
Riley, Nipsco, Infrasource and Myron will meet and go over the progress and
dates at street locations, which Nipsco needs to have done in order to stay out
of the way of Reith Rily. They also are interested in doing some pot holing at
intersections to make sure the lines are not in conflict and having the lines
checked for elevations.
Comcast will be starting their work at
Bartlett next week that work should take a week. The work at Chippewa is still
needing state permits. The City informed Jay that it is a city street now and
the permits are done through the city. The City also inquired about the work in
the down town area and jay will have to get back with them, a different
department is handling that.
AT&T did not show up to the meeting.
Robert Henry went over the work that
they are doing. They should be cleared of the work zone as scheduled.
Water Department the 20 inch main
installed at Bartlett should be operational by Wednesday. The trucks servicing
the building on Bartlett have been able to come in from the North with little
trouble.
The Mar Main Pharmacy Asbestos will be
handled by Memorial Hospital. Demolition can then take place on the 5th
of May.
The utilities and Stake holders left at
this time.
Right of way issues were then review.
Submittals were also reviewed.
Reith Riley questions about RFI #4 the
blocks is still being reviewed by the City. The QC/QA questions can’t be answered
until Reith Riley provides a price.
A paver block sample was requested by
the City for Jitin to review.
Reith Riley asked on the repricing of
the QC/QA HMA if they could use rap in the base and intermediate. The City is
receptive to that but no rap in the surface.
Pemberton Davis then asked about back
plates on traffic signal heads. The City wants the intersections to look
uniform. The signals that are getting relocated will not have back plates. The
only intersections that will are those that have all new signals which should
be Lassalle and Sample.
Pemberton Davis will be making the sign
for in front of the office and have it installed by next week.
JPR asked Reith Riley how long and how
soon they would need to get the endsection on going into the Saint Joe River.
This information is needed to get the waiver. Reith Riley will have to get with
Woodruff to get that answer.