Wednesday, April 27, 2016

4-27-16

Controlling operation: Structure Placement
Fraction of Day workable 10/10
Hi 60 Lo 42
Weather Am cloudy PM Cloudy

Indiana Earth worked on removals on the northwest corner of Bartlett and Michigan. They also placed top soil behind the curbs on Bartlett Street between saint Joe and Riverside.

Woodruff worked on placing structures and pipe on Bartlett Street between Saint Joe and Michigan Street

Reith Riley poured sidewalk on Bartlett Street between Riverside and Saint Joe on the south side of the road. They then poured the sidewalk at the doctors office on the south east corner of Michigan and Bartlett.

Reith Riley also had a asphalt crew patch the watermain work on Michigan this will allow for Michigan traffic configuration to be shifted to 2 lanes north bound and 1 lane southbound.

Pemberton Davis removed the traffic signals at Main and Broadway. They pushed conduit on Main and Indiana. They also turned the light at the intersection of Michigan and Bartlett to green all the time on Michigan and only turns red when the push button is triggered.

Comcast was onsite working on trenching on the northeast corner of Bartlett and Michigan. The work should be completed by Friday.

I met with Denis Bunch today onsite over the AT&T vault at Michigan and Bartlett north west corner. Denis would like to move the vault to behind the curb line. Moving the vault would be in conflict with the new storm sewer being placed. Tony made a suggestion to reroute the storm line. I brought this proposal to the City and they would be receptive to the idea if AT&T would pay for the new structures needed to move the line. I informed Denis of the City's counter proposal and it appears the vault will stay in place.

A






No comments:

Post a Comment