Controlling operation: Pipe and structure installation on Bartlett
Fraction of day workable 10/10
Hi 39 Lo 32
Weather Am cloudy light rain Pm Cloudy light Snow

Woodruff worked on testing and back filling the 20 inch water line at Marion and Michigan. They also worked on laying out pipe and structures on Bartlett Street by Riverside.

Weaver Consulting was on sight testing the backfill Woodruff placed.

Indiana Earth worked on removals on Michigan north of Bartlett.

Went into the Park at Bartlett and counted a number of trees that will need to be removed. Received complaints due to this being a historical district.