Tuesday, April 26, 2016

4-26-16

Controlling operation; Structure placement on Bartlett
fraction of day workable 10/10
Hi 62 Lo 48
Am Cloudy Pm Cloudy

Indiana Earth worked on removing the parking lot on the North West corner of Bartlett and Michigan. They also worked on placing topsoil on Bartlett Street between Saint Joe and Riverside.

Woodruff worked on placing structures on Bartlett Street from saint Joe to Michigan. They rain into an issue with a 6 inch waterline at the intersection of Bartlett and saint Joe. The water-main is in conflict with the storm sewer. The six inch water-main splits into 4 water services right where the storm-line sets. The South Bend water dept was unable to make a decision on where the line run to and will not be able to make the decision until Thursday,

Pemberton Davis worked on the intersection of Michigan and Calvert.

Reith  Riley was having an issue with the AEP pole in the alley between Saint Joe and Michigan on Bartlett. The pole was supose to be removed by March 31st.