Controlling operation: Structure Placement on Bartlett
Fraction of day workable 10/10
HI 58 LO 43
Weather Am Cloudy Rain off and on PM Cloudy

Indiana Earth worked on removals on Bartlett Street at the north east corner of Michigan and Bartlett. They also worked on placing dirt behind the curb on Bartlett between Riverside and Saint Joe. They also worked on rough grading on Bartlett St. just east of Michigan.

Woodruff placed structures on Bartlett Street between Saint Joe and Michigan. We met with Bob Krol, Ed Herman, Toy Vila, and Tony Kasar on site to discuss the connection between structures 811 and 813A. The an issue arose with a conflict with the storm sewer and the water main. I was decided to lower the storm sewer and have no fall in it. This would lower it enough to get under the water line.

Pemberton Davis worked at the intersections of Main and

Comcast got its cable off the pole at the ally on Bartlett street between Saint Joe and Michigan.